Part 2 wood front porch progress.
Replacing porch floor boards.
Click the links below to see the rest of the posts in this project.
Staggered splices look better and make a stronger deck.
Part 4 critter proofing and installing the porch boards.
You might have to remove a couple of courses of siding to make this happen but it s a small price to pay to keep water out of your house.
For this repair project we milled interlocking tongue and groove boards from treated lumber to replace the original rotted porch boards.
Flashing costs about 7 at home centers.
Span that i could tell was the original porch flooring from when the house was built in 1880.
Many construction experts say there s no need to factor in a slope for spaced floorboards since the water can drain through easily.
The new wood porch floor is finished.
It s a good idea to prime all four sides of tongue and groove flooring before installing it to reduce expansion and contraction due to changes in temperature and humidity.
Rinse and let dry.
In the video we will show techniques to replace tongue and groove porch boards both in the middle and.
Rotten porch board are a big issue with historic homes.
If the existing decking is gray weather the new decking with a solution made from 1 cup of baking soda and 1 gallon of warm water.
Slide the flashing up under the house wrap.
This creates joint lines that look out of place in an otherwise jointless porch.
When replacing a porch floor be sure to use pressure treated pine or other rot resistant wood for both the joists and flooring.
Part 3 more front porch progress.
Part 5 finished front porch floor wood front porch built over existing concrete porch.
If the porch floor isn t tongue and groove allow at least between new or replacement boards as you lay them to permit water to flow through the decking.
Use full length flooring boards to preserve the look of the porch.
Damaged joists are more difficult to replace than flooring so flooring damage should be fixed promptly.
I decided to replace the entire side of porch flooring with the exception of a roughly 4 ft.
Do not simply cut out the damaged areas and patch the floor.
Cut out the bad pieces so that the splices are offset by at least one joist width and new boards are at least two joist spaces wide.